News for hackers. Stuff that matters.
Re:Tell HN: My rule of thumb for initial estimation by tomjen3 on Monday August 30, 2010 @01:38PM (#1646898)
That might work for a project, but I guess the number of LOC you can write in any given time depends largely upon which language you write it in.
Re:Tell HN: My rule of thumb for initial estimation by thibaut_barrere on Monday August 30, 2010 @02:04PM (#1646984)
Some projects involve a lot more infrastructure work than coding. Typical example (my current project): setting up a resque/redis queue monitored by god/monit with a simple sinatra front-end (that is less than 100 lines long).

A large part of estimating errors comes from forgetting an area that requires work (eg: in code, deployment, documentation, staging/feedback/iterating...).