Re:Inside Vancouver's Brock Commons, World's Tallest Mass Ti...
by sizzzzlerz on Sunday February 18, 2018 @09:55AM
(#16406317)
So when the building was complete, what were the final costs relative to an equivalent steel and concrete structure? The video said construction took 9-1/2 weeks but there was a lot of pre-planning, mock ups, etc. that wouldn't have necessarily been needed for the steel version. Those extra costs need to be factored in as well, at least until enough experience has been gathered to no longer require it.
[ Parent
| on HN ]
Re:Inside Vancouver's Brock Commons, World's Tallest Mass Ti...
by kazinator on Sunday February 18, 2018 @11:09AM
(#16406671)
It was finished in 2016, after eight months.
According to this article: https://biv.com/article/2016/09/crews-complete-structure-rec...
"The $51.5 million structure is on budget, and Metras expects any future buildings to cost less, as the Brock Commons budget also includes $4.45 million from external agencies to cover first-time costs of using mass timber on such a scale."