Re:Ask HN: Best project management practices in 2018?
by cyberlync on Wednesday February 14, 2018 @12:49PM
(#16377655)
Agile and Scrum (big A/S) have faded into agile and scrum (little a/s). The 'One True and Holy Process' has faded into a set of processes that organization iterates on. The process should be fit to the team/organization. The team/organization should not be fit to the process. Personally, I have had good luck with a mix of kanban, with multipart estimation and Monte-Carlo simulations for projecting completion dates. So far its worked well and managing change while being able to predict completion times.