Re:Ask HN: Best practice for estimating development tasks?
by GrantSolar on Thursday January 11, 2018 @07:31AM
(#16123251)
>Break tasks down to granularity of 1-8 hours. No more than that.
I do this for sub-tasks that are relevant to myself only (for example, "create function to do X"), but my minimum estimates are 1/2 a day (in extreme cases like a 1-line fix) or 1 day for anything that goes to a manager.
I do this for sub-tasks that are relevant to myself only (for example, "create function to do X"), but my minimum estimates are 1/2 a day (in extreme cases like a 1-line fix) or 1 day for anything that goes to a manager.