Re:How to respond when you are asked for an estimate?
by gist on Sunday December 03, 2017 @12:51PM
(#15838582)
Cliche: "Deliver more than you promise"
[ Parent
| on HN ]
Re:How to respond when you are asked for an estimate?
by ghaff on Sunday December 03, 2017 @01:27PM
(#15838737)
Or "Underpromise, overdeliver."
Sometimes there are legitimate reasons to come up with schedules that are as accurate as you can make them, understanding that stuff almost always happens. Sometimes a project or some dependencies don't make sense if they can't be done by a particular date.
But, yeah, it's good advice in general. For most of the work I do (not programming), I have a pretty good sense of the minimum time I need and I almost always significantly pad that to accommodate priority interrupts or just so I can take a bit of extra time if I feel the task warrants it.