Re:Tesla Semi by JoshTriplett on Friday November 17, 2017 @01:23AM (#15719508)
> It also means that on the distribution grid, a charging station for 8 semis will need a dedicated 20 MVA 33/11 kV distribution transformer, plus 4 11kV/480V transformers.

Or a pile of batteries.

Re:Tesla Semi by raverbashing on Friday November 17, 2017 @02:09AM (#15719783)
Sure, and how you're supposed to charge them fast enough to charge incoming trucks

> a charging station for 8 semis will need a dedicated 20 MVA

20MVA is approx. 20MW, Solar Power is 100W/m2 hence that gives 0.2km2 (or 200,000m2 of needed area for 20MW)

Solar won't help you in this case

Re:Tesla Semi by mtgx on Friday November 17, 2017 @06:55AM (#15721250)
Not locally, at least. Utility-wise, it will work out.