Re:Oroville Dam: Cost to repair spillways nearly doubles in ...
by nathancahill on Saturday October 21, 2017 @09:48PM
(#15524691)
Pretty common strategy in bidding. Undercut the second bidder to get the contract, then run over budget to make a profit.
[ Parent
| on HN ]
Re:Oroville Dam: Cost to repair spillways nearly doubles in ...
by yrb on Saturday October 21, 2017 @10:58PM
(#15524929)
The problem as I see it is you don't have to actively run it over budget in bad faith.
Even as an ethical actor you can only price what is specified. However, you can then use your knowledge about likely the real variances that will be needed and risk profile to place a bid that takes this into account to remove margin or discount the bid price.