An 8-hour weekday shift with 2 hours not behind the crane is:
(75.91 * 6) + (73.91 * 2) = 603.28
A five-day week at that rate is 3,016.40.
52 weeks of that is $156,852.80. Add $60k insurance (and it's questionable to bundle that as "pay", but whatever), and we're at $218,652.80. Add $18k for max 401(k) contribution and it's $234,852.80.
From there we need to find $265,147.20 in overtime to get to $500k. If the overtime rate is double time, and if literally every overtime hour worked is behind the crane, our engineer needs 1,747 hours of overtime in a year in order to hit $500,000.
Working at 8-hour shift every weekend day can eat up 832 hours of that, leaving 915 hours we still need to find somewhere else. That's 17.6 hours of overtime per week. If they're only worked on weekdays, the crane operator needs to work an 11.5 hour shift every weekday and an 8 hour shift every Saturday and Sunday, year-round, to hit $500,000.
I'm more than "a little suspicious" of that.
Without, if they work 52 40-hour weeks, it's $156k. Which is good money, but a far, far cry from the "many make half a million" claim.
And since a little bit of "let's actually run the numbers you just presented" reduced the initially claimed amount by nearly 70%, I think it's perfectly reasonable to say the initial claim was not rooted in reality, and probably the real amount is lower yet.
All that information is public. I'm a little suspicious of a $500k crane engineer myself, but you managed to get everything wrong. If you missed half the stuff, and the half that was available in the article and in a two-minute Google, god knows what you're leaving out. I literally had the top result in my first search showing the wage card and here you're busy making up nonsensical numbers.