Re:Musk Bets He Can Fix Aussie Power Woes in 100 Days or It’... by owenversteeg on Friday March 10, 2017 @02:31PM (#13841334)
The source in that image from Tesla are extremely suspicious. A Google search for "IIT Takeshita" gives you only that image. Further research took me to this page. http://www.iit.co.jp/, where I got the plain text "I'm sorry. It is under construction. Please wait."

By the way, your own sources contradict each other - even if you _do_ believe that image from Tesla, the Gigafactory's completed capacity is 35 GWh/yr. This blog post states the same [0]. The segment which is done is cool, but it is surrounded by construction equipment and I doubt it is producing very many cells.

Finally, since I doubt you're in the battery industry, there are two very important numbers: production capacity and production. For example, 2014 worldwide production capacity was almost 30 GWh, but worldwide production was only 5.4 GWh [1]. This is due to a lot of factors, but ultimately only a fraction of manufacturing capacity is used at any given time. A lot of graphs that you see on blogs will conflate the two.

[0] https://www.tesla.com/blog/battery-cell-production-begins-gi...

[1] http://evobsession.com/wp-content/uploads/2016/04/image-23-e...

Re:Musk Bets He Can Fix Aussie Power Woes in 100 Days or It’... by schiffern on Friday March 10, 2017 @03:01PM (#13841597)
>The source in that image from Tesla are extremely suspicious. A Google search for "IIT Takeshita" gives you only that image.

It's not easy to find, but I did some digging. Looks like an analysis of the global battery industry, with the 2013 version presented at the 2013 Battery Japan conference.[1] From other citations I found[2][3] it's clear the speaker is Hideo Takeshita, who in 2001 was the vice president of IIT (the Institute of Information Technology Ltd.)[4] and in 2014 was the president of a battery market research firm called B3 Corporation.[5]

Sure the document isn't freely available online, but given the commercial nature of the content that hardly seems suspicious.

>your own sources contradict each other

Sorry, I should have been more clear. It gets very confusing since it's a moving target, and you can rarely tell who is using what source (and when that source is from).

The original capacity announced in their blog post[6] on 2014-02-26 was 35 GWh/yr at the cell level and 50 GWh/yr at the pack level (importing 15 GWh/yr of cells).[7] That's what you're seeing on the chart.

Later at the 2016 shareholder meeting on 2016-05-31, Tesla CEO Elon Musk announced that they were going to triple the final production capacity at the Nevada Gigafactory.[8]

[1] https://web.archive.org/web/20130207162628/http://www.batter...

[2] http://www.sdle.co.il/AllSites/810/Assets/c%20pillot-avicenn... (page 42)

[3] http://www.avem.fr/docs/pdf/AvicenneDiapoXining.pdf#21 (page 21)

[4] http://electronicdesign.com/energy/li-ion-batteries-reach-hi...

[5] http://wardsauto.com/miscellaneous/battery-experts-seek-lowe...

[6] https://www.tesla.com/blog/gigafactory5

[7] https://www.tesla.com/sites/default/files/blog_attachments/g...

[8] http://electrek.co/2016/05/31/tesla-triple-battery-output-gi...