Re:It Takes 6 Days to Change 1 Line of Code (2015)
by aiiane on Tuesday December 06, 2016 @07:11PM
(#13119425)
This is what escalation is for - the job of a VP or Director of Engineering is to decide what is actually urgent and approve fast-tracking it, and what should actually follow process. Having an efficient escalation process is critical.
[ Parent
| on HN ]
Re:It Takes 6 Days to Change 1 Line of Code (2015)
by dsr_ on Tuesday December 06, 2016 @07:24PM
(#13119480)
Very much this: there should be a process for "emergency change" and that process has to be used for every actual emergency and not for anything else.
Re:It Takes 6 Days to Change 1 Line of Code (2015)
by chewyfruitloop on Wednesday December 07, 2016 @05:32AM
(#13121642)
I've found that those in charge also have a budget to run you on... how do they justify you spending x hours updating code to do exactly 0 as far as anyone is concerned? ..plus all the regression testing?
They just don't... it gets left as it is
Re:It Takes 6 Days to Change 1 Line of Code (2015)
by droopyEyelids on Tuesday December 06, 2016 @08:09PM
(#13119721)
The word "should"