It's a finding from a Capers Jones report (I believe on the analysis of agile vs waterfall projects of varying sizes and durations). I'll see if I can dig up the exact report for you...
That would be like predicting the weather with a single model, once, for the next three months. Of course that isn't going to work.
There are a few key points I think are often overlooked:
* Estimating is less about understanding time, and more about sizing a project and effort -- a study in software economics.
* Bottom-up estimates need to be based on historical performance. They should always be ranges and should include a notion of confidence. They should be democratically created if you're estimating for a team. You can do something simple (like Estimatr) or use a tool with a lot of data behind it (like Personal Software Process) - I do both.
* Top-down estimates should also be used. I often use COCOMO and COSYSMO, with monte carlo risk calculations (http://csse.usc.edu/tools/COCOMOII.php).
* The two approaches will give you two answers (both in ranges), with confidence intervals, which provides you a better sense of the size of the effort.
* Generating and publishing an estimate has a psychological effect on the team - consider that wisely (read Peopleware).
* Estimates are good for about two weeks, after that, they've become stale.
* You're not done with a project until you've recorded your performance data (for future bottom-up estimates).
* If a project is going to last three months or less, the research shows that nothing matters at all -- estimates, process, etc. -- do whatever keeps you/the team motivated.