Hmmm, it wasn't until almost 20 years after I had started programming that I could make solid "off the top of my head" estimates (by the end of the project (C++ multithreading server), per item I was accurate within 30 minutes).
I think it's both a matter of experience including some on the particular project and eliminating the unknown unknowns. Doing the latter is my first priority in a project, e.g. by getting something working end to end ASAP.
Also, to avoid the "working extra hard" trap (what, you aren't already working as hard as it makes sense???), you must always make the estimates in man-hours, not The Mythical Man Month. Then and only then should someone try to turn that into a calendar schedule, allowing for inevitable downtime and so on.
I think it's both a matter of experience including some on the particular project and eliminating the unknown unknowns. Doing the latter is my first priority in a project, e.g. by getting something working end to end ASAP.
Also, to avoid the "working extra hard" trap (what, you aren't already working as hard as it makes sense???), you must always make the estimates in man-hours, not The Mythical Man Month. Then and only then should someone try to turn that into a calendar schedule, allowing for inevitable downtime and so on.