Re:Why Are Projects Always Behind Schedule?
by vitd on Saturday December 19, 2015 @07:39PM
(#10765541)
I'm in an organization that uses this method, and I don't think it helps. I believe our "optimistic" metric is supposed to be something like "We have a 10% chance of hitting this goal," our "realistic" metric is supposed to be something like "We have a 50% chance of hitting this goal" and our pessimistic is "We have a 90% chance of hitting it". (Or something like that. I don't remember the exact values off the top of my head.) But what happens is the engineers estimate what they think it will take, claim that's the "realistic" option, then add or subtract some percentage from that for the pessimistic and optimistic values. Nobody really understands how (or if) it's supposed to work, so the estimates are still bad.
Re:Why Are Projects Always Behind Schedule?
by andrebaaij on Saturday December 19, 2015 @02:26PM
(#10764541)
As a side project, a friend and I are developing a probabilistic scheduling tool "Probaplan". It not only uses PERT but also incorporates risks for more accurate scheduling. Using the planning, risks and PERT distributions we simulate the project in a monte carlo simulation. The result is a distribution of simulated end dates, these dates can be used to say: The probability that the project is finished before June 2016 is 80%.
If anyone is interested in trying out the beta version, drop me an email at andre /at/ thebroadbaycompany.com
Re:Why Are Projects Always Behind Schedule?
by netghost on Saturday December 19, 2015 @04:00PM
(#10764825)
The typical PERT three point distribution is better than assuming the mean, but does have a few drawbacks when modeling joint probable outcomes. I honestly can't remember if it over our under represents the optimistic or pessimistic result.
The other quirk is that it breaks down when you map from effort or work to duration, the actual time something takes when you factor in availability, interruptions, communication costs, etc.
Re:Why Are Projects Always Behind Schedule?
by _paulc on Saturday December 19, 2015 @05:00PM
(#10765061)
I think that the real value is in forcing people to think about optimistic vs worst case estimates - in my experience the initial estimate is almost always actually the optimistic number and when they start to think about risks people tend to become much more conservative.
Re:Why Are Projects Always Behind Schedule?
by danieltillett on Saturday December 19, 2015 @04:03PM
(#10764832)
Is there any reason to use a triangular distribution these days? I can see it made sense in the 1950s, but now it should be trivial to use a more accurate distribution.
[1] https://en.wikipedia.org/wiki/Program_evaluation_and_review_...
The program (or project) evaluation and review technique, commonly abbreviated PERT, is a statistical tool, used in project management, which was designed to analyze and represent the tasks involved in completing a given project. First developed by the United States Navy in the 1950s, it is commonly used in conjunction with the critical path method (CPM).