I am well aware that they don't need a giant gas plant or 250 mw power plant, but that's exactly what they applied for. Your arguments are nonsensical so I stopped replying after repeatedly and calmly explaining the rules to you
SpaceX and FAA snuck a bunch of oil and gas infrastructure including a gas plant, a LNG a 250 MW power plant into an "insignificant/minor change" NEPA environmental review document that was supposed to just be for bigger rockets.
It has tons of basic errors, missing data, and even though NEPA is a public disclosure law, no one is talking about the oil stuff at all Also implied, but explicitly not noted in the document are a 1. Pipeline that needs to be constructed and 2. the huge amount of newly drilled oil and gas wells in a region of Texas that currently has no production to speak of.
Oh and all of this is on a federally protected wildlife reserve. And it's super illegal and unprecedented and brings about all sorts of uncomfortable questions about regulatory capture
From a legal and technical standpoint, My work has been run through legal, environmental, and oil and gas engineers I've worked with over the years.
The FAA is subject to NEPA review, and hence any SpaceX activity in this area must go through the same process as every other industrial activity that impacts federal interests.
EPA definitely has a dog in the fight, especially considering that a 250 megawatt power plant would be a literal "major stationary source" under the clean air act
FAA's document is subject to NEPA and table 2.1 in the PEA considers the gas plant and power plant to be in scope. FAA is the overseeing agency for this action so it doesn't matter that it's not in "FAA's domain"
FERC and DOE do these types of NEPA approvals all the time and include full EPA participation.
SpaceX and FAA didn't consult with EPA and that was likely intentional. This is essentially an unprecedented action under NEPA. Feel free to shoot emails or ask questions. Finally getting lots of attention here.